👋Project Timeline and Phases

The LSLGA-CMS Project is to be executed within the defined time frame. The project is structured to be delivered over 12 weeks, with each phase focusing on a key milestone:

Key Milestones and Timelines

PHASE
WEEKS
KEY DELIVERABLES
SUCCESS METRICS

Kickoff & Planning

Week 1-2

  • Signed NDA/MoU

  • Technical Specifications

  • Risk Assessment Plan

100% Stakeholder Alignment

UI/UX Design

Week 3-4

  • Wireframes

  • Interactive Prototypes

LSLGA Design Approval

Backend Development

Week 5-6

  • Secure Database

  • Functional APIs

  • RBAC Implementation

100% API test coverage

Frontend Development

Week 7-8

  • Operator dashboard

  • Admin Dashboard

Cross-browser compatibility

Integration & Security

Week 9

  • Payment Gateway Integration

  • Encryption/2FA

Penetration Test passed

Testing & QA

Week 10

  • Test Cases

  • UAT Completion

<5 Critical bugs

Deployment & Training

Week 11

  • Production Deployment

  • Training materials

100% Staff trained

Go-Live

Week 12

  • Pilot Launch

  • System Monitoring

99.9% uptime

Current Status

The project is currently in the Kickoff and Planning phase. The necessary business documents are being gathered and the technical specification documents are currently being written. The next phase it will be covering is the Design phase where the wireframes and prototype are being worked on.

Last updated