πProject Timeline and Phases
The LSLGA-CMS Project is to be executed within the defined time frame. The project is structured to be delivered over 12 weeks, with each phase focusing on a key milestone:
Key Milestones and Timelines
Kickoff & Planning
Week 1-2
Signed NDA/MoU
Technical Specifications
Risk Assessment Plan
100% Stakeholder Alignment
UI/UX Design
Week 3-4
Wireframes
Interactive Prototypes
LSLGA Design Approval
Backend Development
Week 5-6
Secure Database
Functional APIs
RBAC Implementation
100% API test coverage
Frontend Development
Week 7-8
Operator dashboard
Admin Dashboard
Cross-browser compatibility
Integration & Security
Week 9
Payment Gateway Integration
Encryption/2FA
Penetration Test passed
Testing & QA
Week 10
Test Cases
UAT Completion
<5 Critical bugs
Deployment & Training
Week 11
Production Deployment
Training materials
100% Staff trained
Go-Live
Week 12
Pilot Launch
System Monitoring
99.9% uptime
Current Status
The project is currently in the Testing Phase. LSLGA is currently runnign their UAt with the test cases and scripts sent to them.
Recent Activities
ACTIVITIES ONGOING
β Test scripts for Admin & Operator portals shared with LSLGA
β PSR shared with the team.
β Ongoing: finalization of SLA/ support contract with legal team.
ACTIVITIES PLANNED
β’ UAT ongoing; results expected Monday, 6th October,
β’ NDA/MoU Review & sign-off
β’ Finalize commercial agreement.
β’ Deployment to LSLGA environment.
Last updated