Project Deliverables

This section encompasses the project deliverables of the LSLGA CMS Project i.e. tangible outputs that the development team will produce. Each deliverable has a specific purpose and contributes to the overall functionality and success of the CMS.

S/N
Key Deliverables
Responsible
Start Date
End Date
Status
Completion

1

Signed MoU

Demi

14-07-25

18-07-25

ONGOING

10%

2

Business Documents

Demi

14-07-25

25-07-25

COMPLETED

100%

3

Technical Specification Doc

Taofeeq

14-07-25

25-07-25

COMPLETED

100%

4

UI/UX Wireframes

Debby

28-07-25

08-08-25

COMPLETED

100%

5

Core API Development

Taofeeq

11-08-25

22-08-25

ONGOING

10%

6

Admin Dashboard Module

Taofeeq

25-08-25

05-09-25

ONGOING

10%

7

Payment Gateway Integration

Taofeeq

08-09-25

12-09-25

NOT STARTED

0%

8

Security Audit Report

Daniel

15-09-25

19-09-25

NOT STARTED

0%

9

UAT Sign-Off Certificate

Demi

22-09-25

26-09-25

NOT STARTED

0%

10

Staff Training

Demi

29-09-25

03-10-25

NOT STARTED

0%

11

Final Project Handover

Demi

06-10-25

10-10-25

NOT STARTED

0%