Project Deliverables
This section encompasses the project deliverables of the LSLGA CMS Project i.e. tangible outputs that the development team will produce. Each deliverable has a specific purpose and contributes to the overall functionality and success of the CMS.
1
Signed MoU
Demi
14-07-25
18-07-25
ONGOING
10%
2
Business Documents
Demi
14-07-25
25-07-25
COMPLETED
100%
3
Technical Specification Doc
Taofeeq
14-07-25
25-07-25
COMPLETED
100%
4
UI/UX Wireframes
Debby
28-07-25
08-08-25
COMPLETED
100%
5
Core API Development
Taofeeq
11-08-25
22-08-25
ONGOING
10%
6
Admin Dashboard Module
Taofeeq
25-08-25
05-09-25
ONGOING
10%
7
Payment Gateway Integration
Taofeeq
08-09-25
12-09-25
NOT STARTED
0%
8
Security Audit Report
Daniel
15-09-25
19-09-25
NOT STARTED
0%
9
UAT Sign-Off Certificate
Demi
22-09-25
26-09-25
NOT STARTED
0%
10
Staff Training
Demi
29-09-25
03-10-25
NOT STARTED
0%
11
Final Project Handover
Demi
06-10-25
10-10-25
NOT STARTED
0%
Last updated