πŸ‘‹Project Timeline and Phases

The LSLGA-CMS Project is to be executed within the defined time frame. The project is structured to be delivered over 12 weeks, with each phase focusing on a key milestone:

Key Milestones and Timelines

PHASE
WEEKS
KEY DELIVERABLES
SUCCESS METRICS

Kickoff & Planning

Week 1-2

  • Signed NDA/MoU

  • Technical Specifications

  • Risk Assessment Plan

100% Stakeholder Alignment

UI/UX Design

Week 3-4

  • Wireframes

  • Interactive Prototypes

LSLGA Design Approval

Backend Development

Week 5-6

  • Secure Database

  • Functional APIs

  • RBAC Implementation

100% API test coverage

Frontend Development

Week 7-8

  • Operator dashboard

  • Admin Dashboard

Cross-browser compatibility

Integration & Security

Week 9

  • Payment Gateway Integration

  • Encryption/2FA

Penetration Test passed

Testing & QA

Week 10

  • Test Cases

  • UAT Completion

<5 Critical bugs

Deployment & Training

Week 11

  • Production Deployment

  • Training materials

100% Staff trained

Go-Live

Week 12

  • Pilot Launch

  • System Monitoring

99.9% uptime

Current Status

The project is currently in the Testing Phase. LSLGA is currently runnign their UAt with the test cases and scripts sent to them.

Recent Activities

ACTIVITIES ONGOING

βœ“ Test scripts for Admin & Operator portals shared with LSLGA

βœ“ PSR shared with the team.

βœ“ Ongoing: finalization of SLA/ support contract with legal team.

ACTIVITIES PLANNED

β€’ UAT ongoing; results expected Monday, 6th October,

β€’ NDA/MoU Review & sign-off

β€’ Finalize commercial agreement.

β€’ Deployment to LSLGA environment.