Project Timeline and Phases

The Intranet Project was executed within a clearly defined time frame and has since transitioned into a continuous maintenance and content improvement cycle.

Project Duration

Kick-Off Date: 14th October, 2024

End Date: 7th February, 2025

Project Milestones

Milestone
Description
Target Date
Status

Project Initiation

Project kickoff, scope definition, and stakeholder alignment

14th October, 2024

βœ… Completed

Design & UI Development

Development of homepage layout, branding, and department pages

Early November 2024

βœ… Completed

Core Page Development

Content buildout for homepage, CEO’s Office, Project Section

Late December 2024

βœ… Completed

Integration of Core Features

Birthday board, EBS Calendar, Forms & Templates, Support widget

Early January 2025

βœ… Completed

Zoho Support Ticket Integration

Embedding support form for IT/helpdesk requests

Mid-January 2025

βœ… Completed

User Testing & Review

Internal testing, feedback collection, and corrections

Late January 2025

βœ… Completed

Go-Live

Full platform deployment and user access

7th February, 2025

βœ… Completed

Continuous Content Updates (Ongoing)

Regular update of sections and documents

Continuous

πŸ”„ In Progress

Current Status

The platform is live and fully operational. Ongoing efforts are focused on

  • Updating existing pages and sections

  • Enhancing user experience based on feedback

  • Ensuring content remains relevant and up-to-date

  • Maintenance of support ticket functionality (via Zoho)

Notes

  • There is no Phase 2 officially planned at this time.

  • Any future enhancements will be treated as incremental updates or change requests handled through the support workflow.