Project Timeline and Phases

The Intranet Project was executed within a clearly defined time frame and has since transitioned into a continuous maintenance and content improvement cycle.

Project Duration

Kick-Off Date: 14th October, 2024

End Date: 7th February, 2025

Project Milestones

Milestone
Description
Target Date
Status

Project Initiation

Project kickoff, scope definition, and stakeholder alignment

14th October, 2024

✅ Completed

Design & UI Development

Development of homepage layout, branding, and department pages

Early November 2024

✅ Completed

Core Page Development

Content buildout for homepage, CEO’s Office, Project Section

Late December 2024

✅ Completed

Integration of Core Features

Birthday board, EBS Calendar, Forms & Templates, Support widget

Early January 2025

✅ Completed

Zoho Support Ticket Integration

Embedding support form for IT/helpdesk requests

Mid-January 2025

✅ Completed

User Testing & Review

Internal testing, feedback collection, and corrections

Late January 2025

✅ Completed

Go-Live

Full platform deployment and user access

7th February, 2025

✅ Completed

Continuous Content Updates (Ongoing)

Regular update of sections and documents

Continuous

🔄 In Progress

Current Status

The platform is live and fully operational. Ongoing efforts are focused on

  • Updating existing pages and sections

  • Enhancing user experience based on feedback

  • Ensuring content remains relevant and up-to-date

  • Maintenance of support ticket functionality (via Zoho)

Notes

  • There is no Phase 2 officially planned at this time.

  • Any future enhancements will be treated as incremental updates or change requests handled through the support workflow.