Project Deliverables

Key Deliverables

This section outlines the major deliverables of the project—the tangible outcomes and functional components expected at various stages of the project. Each deliverable represents a key milestone that contributes to the overall success of the intranet platform.

S/N
KEY DELIVERABLES
RESPONSIBLE
START DATE
END DATE
STATUS
% COMPLETION

1

Sign off PID and share with Interswitch

LightWay MFB

07-04-25

07-04-25

COMPLETED

100%

2

Create Collaborative Channel

Interswitch

07-04-25

07-04-25

COMPLETED

100%

3

Share API Documentation with Customer

Interswitch

07-04-25

07-04-25

COMPLETED

100%

4

API Review and Gap Analysis

LightWay MFB

12-05-25

15-05-25

COMPLETED

100%

5

Test Credentials Provision

Interswitch

15-05-25

15-05-25

COMPLETED

100%

6

API Integration Development

LightWay MFB

12-05-25

12-06-25

COMPLETED

100%

7

End-to-End Testing

Lightway MFB

12-06-25

16-06-25

COMPLETED

100%

8

Compliance & Security Review

Lightway MFB

16-06-25

16-06-25

COMPLETED

100%

10

UAT & Approval to push to prod.

All

16-06-25

19-07-25

COMPLETED

100%

11

Submission of Production Items

LightwayMFB

15-07-25

17-07-25

COMPLETED

100%

12

Production Configuration

Interswitch

12-07-25

22-07-25

COMPLETED

100%

13

Staff Training

Demi

21-07-25

19-09-25

ONGOING

80%

14

Go Live

All

23-07-25

23-07-25

NOT STARTED

Current Project Status

Activities Ongoing

✓Collections implementation tested internally and confirmed working ✓Pilot resumed October 3 – loan application successfully placed

Activities Planned for Next Week

• Manual card payment fix by Interswitch • Auto-debit test planned with adjusted 1-day due date • Dashboard config & training of the Lightway MFB staff. • Staff training pending resolution of repayment tests • Go-live

Last updated