Project Deliverables

Key Deliverables

This section outlines the major deliverables of the project—the tangible outcomes and functional components expected at various stages of the project. Each deliverable represents a key milestone that contributes to the overall success of the intranet platform.

S/N
KEY DELIVERABLES
RESPONSIBLE
START DATE
END DATE
STATUS
% COMPLETION

1

Sign off PID and share with Interswitch

LightWay MFB

07-04-25

07-04-25

COMPLETED

100%

2

Create Collaborative Channel

Interswitch

07-04-25

07-04-25

COMPLETED

100%

3

Share API Documentation with Customer

Interswitch

07-04-25

07-04-25

COMPLETED

100%

4

API Review and Gap Analysis

LightWay MFB

12-05-25

15-05-25

COMPLETED

100%

5

Test Credentials Provision

Interswitch

15-05-25

15-05-25

COMPLETED

100%

6

API Integration Development

LightWay MFB

12-05-25

12-06-25

COMPLETED

100%

7

End-to-End Testing

Lightway MFB

12-06-25

16-06-25

COMPLETED

100%

8

Compliance & Security Review

Lightway MFB

16-06-25

16-06-25

COMPLETED

100%

10

UAT & Approval to push to prod.

All

16-06-25

19-07-25

COMPLETED

100%

11

Submission of Production Items

LightWayMFB

15-07-25

17-07-25

COMPLETED

100%

12

Production Configuration

Interswitch

12-07-25

22-07-25

ONGOING

50%

13

Staff Training

Demi

21-07-25

21-07-25

NOT STARTED

14

Go Live

All

23-07-25

23-07-25

NOT STARTED

Current Project Status

The project is currently at the production configuration stage. This is being done by the Interswitch Team.