Project Deliverables
Key Deliverables
This section outlines the major deliverables of the project—the tangible outcomes and functional components expected at various stages of the project. Each deliverable represents a key milestone that contributes to the overall success of the intranet platform.
1
Sign off PID and share with Interswitch
LightWay MFB
07-04-25
07-04-25
COMPLETED
100%
2
Create Collaborative Channel
Interswitch
07-04-25
07-04-25
COMPLETED
100%
3
Share API Documentation with Customer
Interswitch
07-04-25
07-04-25
COMPLETED
100%
4
API Review and Gap Analysis
LightWay MFB
12-05-25
15-05-25
COMPLETED
100%
5
Test Credentials Provision
Interswitch
15-05-25
15-05-25
COMPLETED
100%
6
API Integration Development
LightWay MFB
12-05-25
12-06-25
COMPLETED
100%
7
End-to-End Testing
Lightway MFB
12-06-25
16-06-25
COMPLETED
100%
8
Compliance & Security Review
Lightway MFB
16-06-25
16-06-25
COMPLETED
100%
10
UAT & Approval to push to prod.
All
16-06-25
19-07-25
COMPLETED
100%
11
Submission of Production Items
LightWayMFB
15-07-25
17-07-25
COMPLETED
100%
12
Production Configuration
Interswitch
12-07-25
22-07-25
ONGOING
50%
13
Staff Training
Demi
21-07-25
21-07-25
NOT STARTED
14
Go Live
All
23-07-25
23-07-25
NOT STARTED
Current Project Status
The project is currently at the production configuration stage. This is being done by the Interswitch Team.
Last updated