Project Timeline and Milestones

The MTN NIPOST Project followed a structured timeline covering development, testing, deployment, and post-launch activities.

Project Duration

MTN VENDING APP

  • Project Start Date: 10th August, 2024

  • Go-Live Date: 10th September, 2025

  • Total Duration: 1year 1 month

MTN ACTIVATION ON THE GO

  • Project Start Date: 10th August, 2024

  • Go-Live Date: 31st January, 2025

  • Total Duration: 5 months

Key Milestones

MTN VENDING APP

Milestone
Start Date
End Date
Responsible
Status

UI Structure/Enhancement

10-08-24

26-08-24

Timothy

COMPLETED

Navigation and User Experience

10-08-24

26-08-24

Timothy

COMPLETED

Reporting and Export

10-08-24

26-08-24

Timothy

COMPLETED

Notifications

10-08-24

02-09-24

Timothy

COMPLETED

Security and Access

10-08-24

04-09-24

Timothy

COMPLETED

Transaction Management

10-08-24

09-09-24

Timothy

COMPLETED

Wallet Management

10-08-24

04-10-24

Timothy

COMPLETED

Commission Management

10-08-24

15-09-24

Timothy

COMPLETED

Risk Management

10-08-24

31-12-24

Timothy

COMPLETED

Flutterwave Integration

10-08-24

02-01-25

Timothy

COMPLETED

UAT

04-09-25

06-01-25

Debby

COMPLETED

Go Live

10-09-25

09-01-25

Timothy

COMPLETED

Integration with MoMo

17-07-25

Taofeeq

ONGOING

Current Status

The project is live and operational as of 10th September, 2025. Current activities focus on:

  • Marketing & Campaign Rollout - driving awareness and user adoption.

MTN ACTIVATION ON THE GO

Milestone
Start Date
End Date
Responsible
Status

Website Landing Page

10-08-24

03-09-24

Timothy

COMPLETED

Screen

10-08-24

03-09-24

Timothy

COMPLETED

Process-Push Notification

10-08-24

03-09-24

Timothy

COMPLETED

Dashboard & Reporting

10-08-24

03-09-24

Timothy

COMPLETED

Stock Pricing & Notification

10-08-24

03-09-24

Timothy

COMPLETED

Integration with Zoho Desk

20-01-25

31-01-25

Taofeeq

COMPLETED

Bike Purchase

20-01-25

31-01-25

Debby

COMPLETED

Design of Branded T-shirts

20-01-25

31-01-25

Debby

COMPLETED

Training of Dispatch rider

20-01-25

31-01-25

Debby

COMPLETED

System Update

17-03-25

31-01-25

Taofeeq

COMPLETED

UAT

10-08-24

03-09-24

Demi

COMPLETED

Go-Live

04-09-25

07-09-24

All

COMPLETED

Sales Reporting

10-08-24

03-09-24

Chris

CONTINUOUS

Current Status

The project is live and operational as of 31st January 2025. Current activities focus on:

  • Follow up with MoMo - regarding the integration of MoMo services.

Last updated