# Project Timeline and Milestones

The **MTN NIPOST Project** followed a structured timeline covering development, testing, deployment, and post-launch activities.

### Project Duration

**MTN VENDING APP**

* Project Start Date: 10th August, 2024
* Go-Live Date: 10th September, 2025
* Total Duration: 1year 1 month

**MTN ACTIVATION ON THE GO**

* Project Start Date: 10th August, 2024
* Go-Live Date: 31st January, 2025
* Total Duration: 5 months

### Key Milestones

<p align="center"><strong>MTN VENDING APP</strong></p>

<table><thead><tr><th width="313">Milestone</th><th>Start Date</th><th width="128">End Date</th><th>Responsible</th><th>Status</th></tr></thead><tbody><tr><td>UI Structure/Enhancement</td><td>10-08-24</td><td>26-08-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Navigation and User Experience</td><td>10-08-24</td><td>26-08-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Reporting and Export</td><td>10-08-24</td><td>26-08-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Notifications</td><td>10-08-24</td><td>02-09-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Security and Access</td><td>10-08-24</td><td>04-09-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Transaction Management</td><td>10-08-24</td><td>09-09-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Wallet Management</td><td>10-08-24</td><td>04-10-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Commission Management</td><td>10-08-24</td><td>15-09-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Risk Management</td><td>10-08-24</td><td>31-12-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Flutterwave Integration</td><td>10-08-24</td><td>02-01-25</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>UAT</td><td>04-09-25</td><td>06-01-25</td><td>Debby</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Go Live</td><td>10-09-25</td><td>09-01-25</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Integration with MoMo</td><td></td><td>17-07-25</td><td>Taofeeq</td><td><mark style="color:blue;">ONGOING</mark></td></tr></tbody></table>

### Current Status

The project is live and operational as of 10th September, 2025. Current activities focus on:

* **Marketing & Campaign Rollout** - driving awareness and user adoption.

<p align="center"><strong>MTN ACTIVATION ON THE GO</strong></p>

<table><thead><tr><th width="264">Milestone</th><th width="115">Start Date</th><th width="104">End Date</th><th width="117">Responsible</th><th>Status</th></tr></thead><tbody><tr><td>Website Landing Page</td><td>10-08-24</td><td>03-09-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Screen</td><td>10-08-24</td><td>03-09-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Process-Push Notification</td><td>10-08-24</td><td>03-09-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Dashboard &#x26; Reporting</td><td>10-08-24</td><td>03-09-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Stock Pricing &#x26; Notification</td><td>10-08-24</td><td>03-09-24</td><td>Timothy</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Integration with Zoho Desk</td><td>20-01-25</td><td>31-01-25</td><td>Taofeeq</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Bike Purchase</td><td>20-01-25</td><td>31-01-25</td><td>Debby</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Design of Branded T-shirts</td><td>20-01-25</td><td>31-01-25</td><td>Debby</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Training of Dispatch rider</td><td>20-01-25</td><td>31-01-25</td><td>Debby</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>System Update</td><td>17-03-25</td><td>31-01-25</td><td>Taofeeq</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>UAT</td><td>10-08-24</td><td>03-09-24</td><td>Demi</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Go-Live</td><td>04-09-25</td><td>07-09-24</td><td>All</td><td><mark style="color:green;">COMPLETED</mark></td></tr><tr><td>Sales Reporting</td><td>10-08-24</td><td>03-09-24</td><td>Chris</td><td>CONTINUOUS</td></tr></tbody></table>

### Current Status

The project is live and operational as of 31st January 2025. Current activities focus on:

* **Follow up with MoMo** - regarding the integration of MoMo services.


---

# Agent Instructions: Querying This Documentation

If you need additional information that is not directly available in this page, you can query the documentation dynamically by asking a question.

Perform an HTTP GET request on the current page URL with the `ask` query parameter:

```
GET https://ebs-projects-knowledgebase.gitbook.io/ebs-projects-knowledgebase/mtn-nipost-project/status/editor.md?ask=<question>
```

The question should be specific, self-contained, and written in natural language.
The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.