Project Timeline and Milestones

The project is scheduled to run throughout 2025, with phased deliverables tied to integration, testing, and go-live activities. The following timeline summarizes the key milestones:

Key Milestones and Deliverables

Milestone/Deliverable
Responsible
Start Date
End Date
Status
Completion

Finalize Technical Scope with Lightspark

PCX / Lightway

07-April-2025

31st-August-2025

COMPLETED

100%

ClearBank (GBP Rail) Integration

PCX / Lightway

07-Apr-2025

07-Apr-2025

ONGOING

50%

MFB (NGN Rail) API Integration

PCX / Lightway

24-Aug-2025

05-Sep-2025

ONGOING

50%

Front-End Build (Lightspark Flow)

PCX

08-May-2025

15-Sep-2025

COMPLETED

100%

Lightspark SDK Integration

PCX

15-May-2025

15-May-2025

NOT STARTED

0%

End-to-End Testing & QA

All Teams

12-May-2025

12-Jun-2025

NOT STARTE

0%

Timeline Highlights

  • April 2025: Project kickoff and initial integrations with Lightspark and ClearBank.

  • May 2025: Planned SDK integration and frontend build initiation.

  • August–September 2025: Finalization of technical scope with Lightspark and MFB integration.

  • June–September 2025: End-to-end testing, QA, and readiness assessments.

  • Expected Completion: September 2025, aligning with delivery goals for the year

Progress Snapshot

  • Overall Project Completion: 50%

  • Key dependencies remain on frontend build and Lightspark SDK integration to unlock testing and QA phases.