Project Timeline and Milestones
The project is scheduled to run throughout 2025, with phased deliverables tied to integration, testing, and go-live activities. The following timeline summarizes the key milestones:
Key Milestones and Deliverables
Finalize Technical Scope with Lightspark
PCX / Lightway
07-April-2025
31st-August-2025
COMPLETED
100%
ClearBank (GBP Rail) Integration
PCX / Lightway
07-Apr-2025
07-Apr-2025
ONGOING
50%
MFB (NGN Rail) API Integration
PCX / Lightway
24-Aug-2025
05-Sep-2025
ONGOING
50%
Front-End Build (Lightspark Flow)
PCX
08-May-2025
15-Sep-2025
COMPLETED
100%
Lightspark SDK Integration
PCX
15-May-2025
15-May-2025
NOT STARTED
0%
End-to-End Testing & QA
All Teams
12-May-2025
12-Jun-2025
NOT STARTE
0%
Timeline Highlights
April 2025: Project kickoff and initial integrations with Lightspark and ClearBank.
May 2025: Planned SDK integration and frontend build initiation.
August–September 2025: Finalization of technical scope with Lightspark and MFB integration.
June–September 2025: End-to-end testing, QA, and readiness assessments.
Expected Completion: September 2025, aligning with delivery goals for the year
Progress Snapshot
Overall Project Completion: 50%
Key dependencies remain on frontend build and Lightspark SDK integration to unlock testing and QA phases.