Project Timeline and Milestones
The MoMo Lightway Finance Project followed a structured timeline covering development, testing, deployment, and post-launch activities
Project Duration
Project Start Date: 19th August, 2024
Go-Live Date: 17th July, 2025
Total Duration: -11 months
Key Milestones
Obtain API credentials (API key, tokens) & configure development environment
19-08-24
26-08-24
Taofeeq
Completed
Authentication module
19-08-24
26-08-24
Taofeeq
Completed
Beneficiary Wallet Validation Module
19-08-24
26-08-24
Taofeeq
Completed
Fund Transfer Module
26-08-24
02-09-24
Taofeeq
Completed
Transaction Monitoring & Logging
26-08-24
04-09-24
SCE
Completed
Platform Testing
02-09-24
09-09-24
Taofeeq
Completed
User Acceptance Testing
09-09-24
04-10-24
Taofeeq
Completed
Deployment
09-09-24
15-09-24
Taofeeq
Completed
Customer Experience & Internal Transactions Testing
31-12-24
31-12-24
Lightway
Completed
Testing & Validation of Transactions with MTN by Stakeholders
02-01-25
02-01-25
All
Completed
Development of Customized Admin Panel for MTN Monitoring
07-01-25
09-01-25
Lightway
Completed
Documentation of User Journeys, Process Flows and Support Docs
07-01-25
09-01-25
Demi
Completed
Go Live
17-07-25
17-07-25
All
Completed
Current Status
The project is live and operational as of 17 July 2025. Current activities focus on:
Marketing & Campaign Rollout - driving awareness and user adoption.
Platform Support & Optimization - ensuring system stability, handling user feedback, and rolling out incremental improvements.