Project Deliverables
Key Deliverables
This section outlines the major deliverables of the project—the tangible outcomes and functional components expected at various stages of the project. Each deliverable represents a key milestone that contributes to the overall success of the intranet platform. Stakeholders can use this list to track what has been completed, what's in progress, and what's planned for future phases.
1
Obtain API credentials (API key, tokens) and configure the development environment
Taofeeq
19-08-24
26-08-24
COMPLETED
100%
2
Authentication Module
Taofeeq
19-08-24
26-08-24
COMPLETED
100%
3
Beneficiary Wallet Validation Module
Taofeeq
19-08-24
26-08-24
COMPLETED
100%
4
Fund Transfer Module
Taofeeq
26-08-24
02-09-24
COMPLETED
100%
5
Transaction Monitoring and Logging
SCE
26-08-24
04-09-24
COMPLETED
100%
6
Platform Testing
Taofeeq
02-09-24
09-09-24
COMPLETED
100%
7
User Acceptance Testing
Taofeeq
09-09-24
04-10-24
COMPLETED
100%
8
Deployment
Taofeeq
09-09-24
15-09-24
COMPLETED
100%
10
Customer Experience & Internal Transactions testing on the platform
Lightway
31-12-24
31-12-24
COMPLETED
100%
11
Testing & Validation of transactions with MTN by Stakeholders
All
02-01-25
02-01-25
COMPLETED
100%
12
Development of customized admin portal for MTN team to monitor transactions
Lightway
02-01-25
06-01-25
COMPLETED
100%
13
Documentation of User journeys, process flows & Support document
Demi
07-01-25
09-01-25
COMPLETED
100%
14
Go Live
All
17-07-25
17-07-25
COMPLETED
100%
Current Project Status
The project is currently live. The current focus is on Marketing, Campaign and Platform Support.
Last updated